Project Overview
Contractor
Buckingham Group
Client
MEPC
Location
Milton Park, Oxfordshire
Duration
12 Weeks
Value
£1.15 million
Sector
Commercial
Milton Park. Oxfordshire.
New commercial office space for an out-of-town technology park
Working for Buckingham Group and MEPC, we constructed a three-story commercial office block at a mixed-use business and technology park in Milton Park, Abingdon. We constructed this scheme following a traditional method using Ischebeck Titan and Doka formwork / falsework.
Scope of works included:
- Three-storeys separate concrete frames, both 6 storeys high
- Reinforced concrete floors
- In-situ concrete cores, walls and columns
- Ischebeck Titan and Doka formwork/falsework
- Associated groundworks
CONCRETE
0
m3
Reinforcement
0
Ton
Concrete Frame
0
m2